You will always know where your project stands.
An architectural commission is split into eight regulated stages. For each one, here is what gets produced, what you approve, and how long it actually takes with us — not the theoretical figure.
A written progress note reaches you every fortnight during design, and every week once on site.
Needs assessment
Needs assessment: brief, site constraints, budget envelope, schedule. We write down what the client is actually after, before drawing anything.
Observed duration: 1 to 3 weeksFeasibility study
Feasibility study: survey, condition report on the existing building, development capacity under the municipal zoning plan, two options tested in 3D and costed.
Observed duration: 2 to 5 weeksPreliminary design
Preliminary design: 1:200 drawings, first SIA 380/1 thermal simulation, cost estimate to ±15%, consultation meetings with the municipality.
Observed duration: 4 to 8 weeksDesign development
Design development: 1:100 drawings, materials fixed, full cost plan following the Swiss CFC classification, estimate to ±10%.
Observed duration: 6 to 10 weeksBuilding permit application
Permit procedure: public enquiry file, response to objections, building permit obtained.
Observed duration: 3 to 6 monthsTendering and award
Tendering: trade-by-trade specifications following the CAN standard, bid comparison, reasoned award recommendations.
Observed duration: 6 to 10 weeksDetailed design
Detailed design: 1:50 technical drawings and 1:5 details, complete IFC model, services coordination with the engineers.
Observed duration: 8 to 14 weeksConstruction
Construction: site supervision, weekly site meetings, cost control by CFC heading, variation management.
Observed duration: 12 to 30 monthsHandover and completion
Handover and completion: acceptance, snagging list, as-built documentation, warranties.
Observed duration: 2 to 4 monthsOperation
Operation: monitoring of actual energy use over the first year, defects cleared before the warranty expires.
Observed duration: 2 yearsReply within 48 hours
Any written request gets an answer within two working days, even if the answer is that the full reply will take a week.
Site report within 24 hours
The site meeting report goes out the next morning and stands as the record. An in-house rule since 2013.
Estimates held to ±10%
From detailed design onwards, the gap between our estimate and the bids received stays under 10% on 9 projects out of 10.