Reuse: four lessons from our sites
Reuse is not cheaper. It costs differently, and above all earlier. Here is what three projects taught us.
Reuse is often presented to us as a saving. Across our last three projects, that was true once out of three. The carbon saving, on the other hand, was constant.
1. The resource survey must come before the competition
Identifying material stocks after planning submission is too late: the drawing is frozen and the quantities are wrong.
2. Insurance remains the hard point
Reclaimed products must be requalified. Testing budgets run at 1.5 to 3% of the relevant package.
3. Storage is planned like any other package
You need covered floor area, for six to fourteen months. At Martinet Hall, we found it on site.
4. Local contractors follow, if warned early
Three quarters of the contractors consulted agreed, provided they were involved from technical design stage.